openCCS
A collaboratively developed handbook for delivering CCS projects

Project Delivery - Top Level Overview

Areas Identify Evaluate Define Execute Operate Closure
General Approach Consider high-level options
Short list options for further study
“What could it be?"
Examine short-listed options and suboptions
Establish if any fatal flaws
Select one best option for taking forward
“What should it be?
Examine selected option and provide further definition to allow investment decision to be made
Demonstrate the technical and economic viability of the project; “What will it be?”
Be capable of being audited by third parties (i.e. peer reviewers, bank
Undertake remaining (detailed) design
Build organisation to commission and manage asset
Undertake construction activities
Undertake commissioning
Operate the asset within regulatory compliance requirements, for the operating life of the asset Decommission asset to regulatory compliance requirements
Rehabilitate site for future defined use
Build organisation and provide resources for post-closure
Specifics for Capture Concept Studies
Identify potential of the new or expanded business
Consider new-build or retrofit for capture
Consider saline reservoir or EOR or other for storage/beneficial reuse
Document general features of the project
Estimate order of magnitude costs of the project (both capital (+/- 30-35% accuracy) and operatin
Prefeasibility Studies
Consider different capture technologies
Consider different EPC contractors
Consider different process, location and project configuration options
Consider different capacities for the project
Assess the likely technical and economic viability of the project
Recommend the preferred option and size for final study
Estimate costs of the project (both capital (+/- 20-25% accuracy) and operating (+/- 10-15% accuracy)
Feasibility Studies
Undertake front end engineering design (FEED) studies, clearly recommending one processing, location and project configuration, and prevent the need to be materially varied after project commitment
Estimate costs of the project (both capital (+/- 10-15% accuracy) and operating (+/- 5-10%; closer to 5% accuracy))
Select construction contractor and delivery approach (i.e. EPC)
Obtain all required regulatory approvals
Provide the basis for making an investment decision, and make final investment decision for construction of capture facilit
Project Execution
Complete the design detail for building the carbon capture asset
Build the organisation and systems to manage the carbon capture asset
Build the carbon capture asset
- On time
- On budget
- To scope and quality
Commission the carbon capture asset to operating stat
Asset Operation
Ramp-up operation of the carbon capture asset to ascertain true performance
Modify the carbon capture asset (as necessary) to achieve required performance
Operate the carbon capture asset to achieve required performance over asset life
Maintain the carbon capture asset to achieve required asset life
Modify the carbon capture asset to comply with legislated regulatory changes
Modify the carbon capture asset to realise identified opportunities
Asset Decommissioning
Operation of asset (i.e. power plant with capture) ceased
Modify the asset (as necessary) to achieve required decommissioned state
- On time
- On budget
- To scope and quality
Asset sites decommissioned and rehabilitated to required condition
Establish organisation for post-closure stage (as necessary)
Specifics for Transport Concept Studies
Consider pipeline or other CO2 transport options
Consider existing or new transport route
Consider single or multi-user transport route
Estimate order of magnitude costs of the project (both capital (+/- 30-35% accuracy) and operating (+/- 15-20% accuracy)
Prefeasibility Studies
Consider different capture technologies
Consider different EPC contractors
Consider different process, location and project configuration options
Consider different capacities for the project
Assess the likely technical and economic viability of the project
Recommend the preferred option and size for final study
Estimate costs of the project (both capital (+/- 20-25% accuracy) and operating (+/- 10-15% accuracy)
Feasibility Studies
Undertake front end engineering design (FEED) studies, clearly recommending one transport route
Estimate costs (both capital (+/- 10-15% accuracy) and operating (+/- 5-10%; closer to 5% accuracy))
Select construction contractor and delivery approach (i.e. EPC)
Obtain all required regulatory approvals
Make final investment decision for construction of transport facilitie
Project Execution
Complete the design detail for building the transport asset
Build the organisation and systems to manage the transport asset
Build the transport asset
- On time
- On budget
- To scope and quality
Commission the transport asset to operating stat
Asset Operation
Operate the transport asset to achieve required performance over asset life
Maintain the transport asset to achieve required asset life
Modify the transport asset to comply with legislated regulatory changes
Modify the transport asset to realise identified opportunities
Asset Decommissioning
Operation of asset (i.e. pipeline) ceased
Modify the asset (as necessary) to achieve required decommissioned state
- On time
- On budget
- To scope and quality
Asset sites decommissioned and rehabilitated to required condition
Establish organisation for post-closure stage (as necessary
Specifics for Storage Site Screening Studies
Define screening basis
Develop screening plan
Review available data and identify potential sites
Estimate capacity and level of uncertainty
Shortlist storage site
Site Assessment Studies
Obtain exploration permit
Define selection basis and develop selection plan
Acquire data, test, analyse, rank risks
Select site and engineering concep
Site Selection Studies
Specify performance targets
Prepare CO2 storage development plan
Evaluate compliance with regulations and qualification goal
Obtain storage permi
Design and (Initial) Construct
Select construction contractor and delivery approach for (initial) storage assets (i.e. EPC)
Complete the design detail for building the (initial) storage assets (i.e. wells, feeder piping)
Build the organisation and systems to manage the storage assets
Build the (initial) storage assets
- On time
- On budget
- To scope and quality
Commission the (initial) storage assets to operating state
Operate (Remaining Construct)
Operate the storage assets to achieve required performance over asset life
Develop plan for permit review/requalification
Reassess risks
Adjust performance targets
Adjust CO2 storage development plan
Storage permit renewal
Complete the design detail for building the (remaining) storage assets (i.e. wells, feeder piping)
Select construction contractor and delivery approach for (remaining) storage assets (i.e. EPC)
Close
Assess if conditions for site closure have been met
Define closure basis
Develop closure plan
Update storage performance forecast and environmental impact assessment
Obtain certificate of fitness for closure
Initiate decommissioning
Transfer of responsibility for site