CO2 Source for Transport in the Closure phase
Objective
To ensure the decommissioning of the CCS chain considers the impact of out-of-specification CO2 encountered during decommissioning.
Major Deliverables
- Input to decommissioning philosophy
- Input to closure and decommissioning plan for transport
Tasks
Note decommissioning of pipeline covered in project development approach and pipeline route approach. Decommissioning of CO2 Booster plant covered in CO2 booster plant. Specific tasks include the following:
- Identify where decommissioning activities will result in out of specification CO2 entering, within or leaving the transport system
- Assess the impact of out of specification CO2during the decommissioning process. This should consider:
- The extent to which CO2 will be out of specification
- Cumulative impacts taking into account any previous incidents of out of specification CO2
- Any potential hazardous, health and safety or environmental impacts
- Impacts on pipeline, infrastructure and equipment including damage affecting potential resale value
- Identify where impacts must or could be prevented or mitigated
- Communicate with capture, transport and storage decommissioning teams to ensure final decommissioning plan takes full account of the impacts of out of specification CO2 during decommissioning
- Identify safe places for venting
- Review and mitigate against JT effect to avoid dry ice formation..
- Identify tasks to be carried out for decommissioning of CO2 conditioning equipment and produce decommissioning procedures for the tasks. This equipment may include:
- Additional cleaning of CO2 source before/after capture/conditioning e.g. water wash, dehydration, sulphur removal
- Additional treatment of captured/conditioned CO2 partway along transport route e.g. additional treatment when transferring between pipelines or changing diameter of pipeline (note CO2 booster plant covered in CO2 booster plant
- Cooling/heating required to offset temperature impacts of pressure changes
Decommissioning tasks may include:
- Final testing of equipment
- Reduction in pressure of conditioning equipment
- Introduction of nitrogen or dry air to equipment as CO2 is flushed from system;
- Final shutdown of equipment
- Use of equipment to reduce pressure in pipeline after capture plant final shutdown
- Venting of CO2, a mixture of CO2 and other gas(es), and/or other gas(es) from equipment before decommissioning of pipeline
- Isolation and removal of all electrical supplies, control systems, instrumentation and other services from the conditioning system
- Removal of all chemicals, wastes and oils from bearing, tanks and pipework prior to the start of dismantling to avoid local pollution and/or contamination
- Permanent sealing of interconnections to conditioning equipment
- Removal of conditioning equipment from injection site for resale or recycle as scrap
- Provide input to decommissioning philosophy
- Perform market sounding exercise to assess resale of high value and saleable plant equipment (e.g. dehydration units, heaters, coolers, control and monitoring equipment, spares etc.) and / or scrap value of CO2 conditioning equipment
- Provide input to decommissioning plan and cost estimate
- Identify resources for the decommissioning activities
- Prepare safe work and environemtnal management procedures to ensure decommissioning and demolition works will be carried out in a safe, secure and environmental acceptable way
Examples
Key Personnel
- Project manager and staff (project controller and document controller)
- Transport or pipeline work-stream lead
- Pipeline operator
- MMV and control system operator
- Project engineers
- Pipeline engineers
- Key engineering sub-consultants
- HAZOP team
