Infrastructure Management for Power Capture in the Execute stage
Table of Contents
Objective
- Complete the detail design to issue for construction quality
- Prepare engineering requisition packages and procure all equipment, bulk materials, consumables and first fills
- Execute contracts for the construction or delivery of infrastructure associated with selected power plant and capture plant options
- Construct, pre-commission, commission, test and handover the facility to operations
- Support the construction activities with engineering and procurement
- Audit and review of construction activity compliance with quality and statutory requirements.
- Overview and participate in safety and environmental management.
- Prepare all documentation to enable the safe operations and maintenance of the facility
- Execute third party supply agreements.
Major Deliverables
- Plans for the management of engineering, prourement, construction, quality, health & safety, environment, emergency response, precommissioning, commissioning, testing, handover and acceptance.
- Completed the detail design to issue for construction quality
- Prepare engineering requisition packages and procure all equipment, bulk materials, consumables and first fills
- Built facilities
- As built documentation
- Executed major utilities contracts such as water supply, HV access, connection and supply fuel supply, cooling water, steam if provided.by an external party
- Executed consumables supply agreements as well as any other support services e.g. emergency response.
Tasks
Specific tasks include the following:
- Finalistion of contracts and execution strategy
- Prepare updated work scopes, functional specifications and minimum standards for any new engineering deliverables
- Review lessons learnt applicable to this phase
- Prepare, review and implement all plans for the management of engineering, documentation, contracting and procurement, quality, construction, HS&E, completion, testing, commissioning, handover and acceptance.
- Execute major EPCM contracts for required functional start up and operation of the power plant and associated capture unit. These may include:
- Civil and Electrical HV connection works including:
- Initiate civil engineering work on site
- Undertake key critical procurement requirements
- Initiate generator connection procedures
- Transformer and protection system
- Transmission line
- Design, supply and construction of gas conditioning systems associated with the supply of gaseous fuel e,g, natural gas if required including:
- Filtration and coalescing system
- Pressure reducing and conditioning station
- Fiscal flow metering
- Safety, pressure relief, and emergency shut-off systems
- Complete civil and mechanical works of water abstraction systems (for direct sea-water cooling) or alternative cooling systems (air-cooled condenser, cooling towers etc)
- Complete civil and mechanical works for storm-water & drainage systems
- Procure and install IT/communications
- Design and construct welfare facilities, control and administration buildings, access roads and site security
- Execute contracts required for infrastructure associated with power capture plant. These may include:
- generator connection agreement, which typically entails:
- Initial connection enquiries to distribution network operator (DNO) and market operator (if different)
- Formal connection agreement application
- Negotiation and finalisation of agreement
- Power supply agreement(s) with electricity supply retailer (if different from associated power asset operator
- Gas supply agreement(s) with gas supply retailer
- Procurement of infrastructure connection systems (if excluded from main power station, distribution works and capture plant contract)
- Supply agreements for heat/steam/fuel/water supply
- Supply agreements for capture process e.g. solvent, oxygen
- Waste disposal agreement(s)
- Review engineering deliverables
- Review and incorporate Vendor Data.
- Complete all RAM analysis and prepare inspection and maintenance plans and procedures
- Carry out Hazard 4 and 5 studies and Risk reviews
- Carry out Control System Hazard Studies and SIL reviews.
- Prepare pre-commissioning, testing, commissioning, handover and acceptance plans and procedures.
- Undertake pre-commissioning, testing, commissioning, handover and acceptance activities.
Examples
- Cost and Performance Baseline for Fossil Energy Plants, Volume 1: Bituminous Coal and Natural Gas to Electricity, 2010 Edition
- Study and Estimate for CO2 Capture Facilities for the proposed 800MW Combined Cycle Power Plant - Tjeldbergodden, Norway
- Cost and Performance of Carbon Dioxide Capture from Power Generation
Key Personnel
- Project Manager and staff (Project Controller and Document Controller)
- Engineering work-stream lead
- Process work-stream lead
- Project Engineers
- Key Engineering Subcontractors
- Process Providers
- Suppliers of power, heat, other required utilities
This content expresses the point of view of individuals in the CCS community and not necessarily the views of their organisation or the Global CCS Institute.