Infrastructure Management for Power Capture in the Identify stage
Objective
To identify the requirements, constraints and costs of infrastructure for the power and capture plant options.
Major Deliverables
- Identification of main requirements for each power, capture plant option:
- Rail, road
- Electrical power connections (high voltage (HV), medium voltage (MV), and low voltage (LV))
- Heat/steam
- Land
- Raw and demineralised water
- Cooling water, storm water
- Gas or other fuels
- Waste management
- Information technology (IT)/communications
- Sewerage and storm-water drainage
- Fire water or other protection systems
- Solvent, oxygen/nitrogen, other chemicals supplies
- Stores
- Laboratory, office, workshops if required
- Identification of potential infrastructure-related constraints for each capture option
- Identification of potential solutions and indicative costs for these constraints
Tasks
Specific tasks include the following:
- List all capture options under consideration (location/type/size)
- Identify at a high level likely requirements of each capture method or capture/power pnat combination in terms of:
- Rail, road
- Electrical power connections (high voltage (HV), medium voltage (MV), and low voltage (LV))
- Heat/steam
- Land
- Raw and demineralised water
- Cooling water, storm water
- Gas or other fuels
- Waste management
- Information technology (IT)/communications
- Sewerage and storm-water drainage
- Fire water or other protection systems
- Solvent, oxygen/nitrogen, other chemicals supplies
- Stores
- Laboratory, office, workshops if required.
- Identify where any of these requirements would be problematic at that location/power plant site. This may include, e.g. consideration of:
- Impact of reduction in power output on power supply agreements in place
- Availability of land
- Cooling water extraction and discharge licences already in place at that location
- Supply chain availability for inputs to process
- Disposal of waste material produced from the capture process
- Access to existing facility for retrofit
- Identify possible mitigation methods for issues identified. This should include consideration of resulting impacts. These mitigation methods may include:
- Dedicated additional plant and/or boilers to provide power and/or steam to capture process
- Modular construction of capture plant and/or placing some modules/equipment above others to maximise use of space
- Purchase of additional land
- Location of some elements of capture plant at a distance from power plant, with ducting/pipework as required
- Air-cooling
- On-site production of oxygen, nitrogen
- On-site waste treatment system and recycling
- Careful planning for retrofit works to be carried out during plant long term shutdown period to minimise plant downtime
- Produce written description of issues associated with infrastructure for each capture option and whether any are potential fatal flaws.
- Identify major differences in infrastructure requirements and determine whether any can be used to eliminate options
- Identify alternatives for providing the required infrastructure and/or possible solutions to constraints and issues.
- Identify tasks to be undertaken on remaining options to enable decisions to be made in the evaluate stage
Examples
- Cost and Performance Baseline for Fossil Energy Plants, Volume 1: Bituminous Coal and Natural Gas to Electricity, 2010 Edition
- Study and Estimate for CO2 Capture Facilities for the proposed 800MW Combined Cycle Power Plant - Tjeldbergodden, Norway
- Cost and Performance of Carbon Dioxide Capture from Power Generation
Key Personnel
- Project Manager and staff (Project Controller and Document Controller)
- Engineering work-stream lead
- Process work-stream lead
- Project Engineers
