openCCS
A collaboratively developed handbook for delivering CCS projects

openCCS Navigation List

High level framework

  Power capture Transport Storage
Identify stage Concept Studies
  • Identify potential of the new or expanded business
  • Consider new-build or retrofit for capture
  • Consider saline reservoir or EOR or other for storage/beneficial reuse
  • Document general features of the project
  • Estimate order of magnitude costs of the project (both capital (+/-30-35% accuracy) and operating (+/-15-20% accuracy))

All articles on Power Capture in the Identify stage...

Concept Studies
  • Consider pipeline or other CO2 transport options
  • Consider existing or new transport route
  • Consider single or multi-user transport route
  • Estimate order of magnitude costs of the project (both capital (+/-30-35% accuracy) and operating (+/-15-20% accuracy))

All articles on Transport in the Identify stage...

Site Screening Studies
  • Define screening basis
  • Develop screening plan
  • Review available data and identify potential sites
  • Estimate capacity and level of uncertainty
  • Shortlist storage sites

All articles on Storage in the Identify stage...

Evaluate stage Feasibility Studies
  • Consider different capture technologies
  • Consider different EPC contractors
  • Consider different process, location and project configuration options
  • Consider different capacities for the project
  • Assess the likely technical and economic viability of the project
  • Recommend the preferred option and size for final study
  • Estimate costs of the project (both capital (+/-20-25% accuracy) and operating (+/-10-15% accuracy))

All articles on Power Capture in the Evaluate stage...

Prefeasibility Studies
  • Consider different transport routes
  • Recommend the preferred transport route and capacity for final study
  • Estimate costs of the project (both capital (+/-20-25% accuracy) and operating (+/-10-15% accuracy))

All articles on Transport in the Evaluate stage...

Site Assessment Studies
  • Obtain exploration permit
  • Define selection basis and develop selection plan
  • Acquire data, test, analyse, rank risks
  • Select site and engineering concept

All articles on Storage in the Evaluate stage...

Define stage Feasibility Studies
  • Undertake front end engineering design (FEED) studies, clearly recommending one processing, location and project configuration, and prevent the need to be materially varied after project commitment
  • Estimate costs of the project (both capital (+/-10-15% accuracy) and operating (+/-5-10%; closer to 5% accuracy))
  • Select construction contractor and delivery approach (i.e. EPC)
  • Obtain all required regulatory approvals
  • Provide the basis for making an investment decision, and make final investment decision for construction of capture facility

All articles on Power Capture in the Define stage...

Feasibility Studies
  • Undertake front end engineering design (FEED) studies, clearly recommending one transport route
  • Estimate costs (both capital (+/-10-15% accuracy) and operating (+/-5-10%; closer to 5% accuracy))
  • Select construction contractor and delivery approach (i.e. EPC)
  • Obtain all required regulatory approvals
  • Make final investment decision for construction of transport facilities

All articles on Transport in the Define stage...

Site Selection Studies
  • Specify performance targets
  • Prepare CO2 storage development plan
  • Evaluate compliance with regulations and qualification goal
  • Obtain storage permit

All articles on Storage in the Define stage...

Execute stage Project Execution
  • Complete the design detail for building the carbon capture asset
  • Build the organisation and systems to manage the carbon capture asset
  • Build the carbon capture asset
    • On time
    • On budget
    • To scope and quality
  • Commission the carbon capture asset to operating state

All articles on Power Capture in the Execute stage...

Project Execution
  • Complete the design detail for building the transport asset
  • Build the organisation and systems to manage the transport asset
  • Build the transport asset
    • On time
    • On budget
    • To scope and quality
  • Commission the transport asset to operating state

All articles on Transport in the Execute stage...

Design and (Initial) Construct
  • Select construction contractor and delivery approach for (initial) storage assets (i.e. EPC)
  • Complete the design detail for building the (initial) storage assets (i.e. wells, feeder piping)
  • Build the organisation and systems to manage the storage assets
  • Build the (initial) transport asset
    • On time
    • On budget
    • To scope and quality
  • Commission the (initial) storage assets to operating state

All articles on Storage in the Execute stage...

Operate stage Asset Operation
  • Ramp-up operation of the carbon capture asset to ascertain true performance
  • Modify the carbon capture asset (as necessary) to achieve required performance
  • Operate the carbon capture asset to achieve required performance over asset life
  • Maintain the carbon capture asset to achieve required asset life
  • Modify the carbon capture asset to comply with legislated regulatory changes
  • Modify the carbon capture asset to realise identified opportunities

All articles on Power Capture in the Operate stage...

Asset Operation

  • Operate the transport asset to achieve required performance over asset life
  • Maintain the transport asset to achieve required asset life
  • Modify the transport asset to comply with legislated regulatory changes
  • Modify the transport asset to realise identified opportunities

All articles on Transport in the Execute stage...

Operate (Remaining Construct)

  • Operate the storage assets to achieve required performance over asset life
  • Develop plan for permit review/re-qualification
  • Reassess risks
  • Adjust performance targets
  • Adjust CO2 storage development plan
  • Storage permit renewal
  • Complete the design detail for building the (remaining) storage assets (i.e. wells, feeder piping)
  • Select construction contractor and delivery approach for (remaining) storage assets (i.e. EPC)

All articles on Storage in the Operate stage...

Closure stage Asset Decommissioning
  • Operation of asset (i.e. power plant with capture) ceased
  • Modify the asset (as necessary) to achieve required decommissioned state
    • On time
    • On budget
    • To scope and quality
  • Asset sites decommissioned and rehabilitated to required conditionEstablish organisation for post-closure stage (as necessary)

All articles on Power Capture in the Operate stage...

Asset Decommissioning
  • Operation of asset (i.e. pipeline) ceased
  • Modify the asset (as necessary) to achieve required decommissioned state
    • On time
    • On budget
    • To scope and quality
  • Asset sites decommissioned and rehabilitated to required conditionEstablish organisation for post-closure stage (as necessary)

All articles on Transport in the Closure stage...

Close
  • Assess if conditions for site closure have been met
  • Define closure basis
  • Develop closure plan
  • Update storage performance forecast and environmental impact assessment
  • Obtain certificate of fitness for closure
  • Initiate decommissioning
  • Transfer of responsibility for site

All articles on Storage in the Closure stage...

All articles on project development activity

Power capture

Transport

Storage

Identify

Back to top

Evaluate

Back to top

Define

Back to top

Execute

Back to top

Operate

Back to top

Close

Back to top

Identify

Back to top

Evaluate

Back to top

Define

Back to top

Execute

Back to top

Operate

Back to top

Close

Back to top

Identify

Back to top

Evaluate

Back to top

Define

Back to top

Execute

Back to top

Operate

Back to top

Close

Back to top